i45NOW
2 hours ago
Northbound Gulf Freeway construction shrinks lanes down to one between Dickinson, La Marque
• Runs Friday, 9 PM - Monday, 5 AM
As work continues on the $230 million Interstate 45 expansion project between FM 517 to FM 1764, a number of northbound closures will start Friday (5/10/2024) night at 9 PM and end Monday (5/13/2024) at 5 AM.
During this closure, there will be one lane open for northbound traffic on I-45 and one lane open on the northbound feeder.
All northbound entrance and exit ramps between FM 1765 and FM 517 will be closed.
The entrance ramp for the Emmett F Lowry Expressway to the northbound lanes will also be closed.
To avoid heavy traffic, take SH 3 or SH 146.
Crews will be moving and placing concrete barriers to guide vehicles away from work, placing pavement markers on the new lanes, and modifying entrance and exit ramps for northbound I-45 traffic.
The project between FM 517 to FM 1764 is expected to be completed in Summer 2026.